How Fastned built a new station nearly emission free
Sustainable mobility is a noble goal, but it’s also crucial that we reduce emissions when building fast charging infrastructure. To this end, our newest fast charging station, opened in early 2023, was largely an emission free build.
Located at the Lingehorst service area along the A2 near Beesd, The station, with its eight charging hubs, was a pilot that informed Fastned’s ambition to reduce construction-phase emissions across future stations.
For the Lingehorst construction-phase scenario, modelled on-site emissions from mobile machinery were 81.85% lower for NOx, a reduction of 22.1 kg/year, and 77.15% lower for CO2e, a reduction of 6,222.2 kg/year, than in the comparable conventional-equipment scenario. The calculation excluded emissions from electricity generation and construction-related traffic. An independent research company prepared the comparison. NOx emissions were modelled with AERIUS Calculator version 2021.2.2, while CO2e was calculated using the stated emission factors. The assessment covered on-site mobile machinery only and excluded electricity-generation and construction-traffic emissions.
Electric machinery at Lingehorst: lessons from a lower-emission construction pilot
During the various construction phases, we used electrical equipment as much as possible. We worked with, among others, electric crawler excavators, wheel loaders, a rammer, a bandsaw, a vibratory plate, and aerial work platforms. A special container was set up to safely charge the electrical equipment at night.
For the Lingehorst assessment, the electric machinery used reduced on-site NOx and CO2e compared with the conventional-equipment scenario. The assessment did not cover all life-cycle or upstream impacts, including emissions associated with generating the electricity. The electric machines used during the pilot produced no direct combustion exhaust at the point of use. Any claim about reduced vibration should be supported by machine-specific measurements or manufacturer data and should not be presented as applying to every machine or the whole site. Where supported by equipment specifications or site measurements, the electric machines used in the pilot operated with lower noise and vibration than comparable combustion equipment. This may reduce disturbance on site, but the result depends on the machine, operating conditions and surrounding activities. In addition, most electrical machines turned out to be stronger than their traditional counterparts, due to the size and weight of the electric battery packs.
Bumps in the road
In some cases, we had to revert to traditional equipment. This was due to unexpected power failures and limited availability of machines, combined with the fast pace of construction. For instance, one of the electric crawler cranes temporarily failed to charge properly. So, to meet the tight schedule we had to use a traditional shovel.
The need to charge electric equipment on site posed another challenge. Lingehorst was suitable for the pilot as it already had a working grid connection. But this is the exception rather than the rule. It would be a welcome step if grid operators prioritised construction projects that demonstrate lower construction-phase emissions and a measurable contribution to reducing NOx or CO2e.
Another challenge was the need to rent electrical equipment for the construction of this fast-charging station. Availability was limited and the equipment significantly more expensive than traditional alternatives. We welcome the €60-million government subsidy announced for the purchase of zero-tailpipe-emission or lower-emission construction machinery, subject to the scheme’s eligibility criteria.
Reducing construction emissions across future stations
The learnings from this first pilot are valuable for our efforts to reduce construction-phase emissions in future station projects. We realise we need to monitor costs as a commercial company, while staying on track with our ambitious growth targets. To strike the right balance, we, together with our partners, are continuously looking for further improvements to the construction process.
But of course, impact comes with scale – the more builders start sharing our commitment to reducing emissions the more progress we will make.For lower-emission construction methods to become more widely adopted, governments could consider emissions performance in tenders and permitting, subject to applicable rules.
Right now, stricter regulations for nitrogen seem to actually slow down these procedures in the Netherlands. We believe construction methods that demonstrate lower NOx emissions should be considered in relevant tendering and permitting processes, in accordance with applicable rules and supported by transparent calculation methods.
Fastned would like to work with government and grid operators to support the transition to electric driving and lower-emission construction.